PMP Communications ITTO

Terms

undefined, object
copy deck
What are the inputs for Communications planning?
Enterprise Environmental Factors, Organizational Process assets, Project Scope statement, Project Management Plan
What are the tools and techniques for Communications Planning?
Communications requirements analysis, Communications technology
What are the outputs for Communications Planning?
Communications Management plan
What are the inputs for Information Distribution?
Communications management plan
What are the tools and techniques for Information Distribution?
Communications skills, Information gathering and retrieval systems, Information Distribution methods, Lessons learned process
What are the outputs for Information distribution?
Organizational process assets (updates), Requested changes
What are the inputs for Perormance Reporting?
1. Work Performance Information
2. Performance Measurements
3. Forecasted Completion
4. Quality control measurements
5. Project Management Plan
6. Approved Change requests
7. Deliverables
What are the tools and techniques for Performance Reporting?
1. Information presentation tools
2. Performance information gathering and compilation
3. Status review meetings
4. Time reporting systems
5. Cost reporting systems
What are the outputs for Performance Reporting?
1. Performance Reports
2. Forecasts
3. Requested Changes
4. Recommended corrective actions
5. Organizational process assets
What are the inputs for Manage Stakeholders?
1. Communications Management Plan
2. Organizational process assets
What are the tools and techniques for Manage Stakeholders?
1. Communication methods
2. Issue logs
What are the outputs for Manage Stakeholders?
1. Resolved issues
2. Approved change requests
3. Approved Corrective actions
4. Organizational Process Assets
5. Project Management Plan